Private Utility – Turbine Installation

This hydro powerhouse project was located in a remote section of land and required detailed planning for deliveries due to limited access and laydown area. With the site being a green field project, surveying and layout were a large part, and paved way for the excavation and installation of the concrete support structure.

The project also included the installation of the steel structure, generator assembly, actuators, turbine, turbine runner, draft tube, piping and all other major components. Platinum Industrial also provided all of the critical alignment and documentation for the project.

The project’s success can be attributed to Platinum Industrial’s attention to detail and knowledgeable team of skilled and dedicated craftsmen.

WWTP Large Bore Pipe Upgrades